Building guide

A general reference on what you will need to plan, permit, and build on your property.

Disclaimer: This guide is general information, not legal, engineering or surveying advice. It may be incomplete, and requirements change. Requirements are set by Indian River County, the St. Johns River Water Management District, the State of Florida, FPL, the Florida Atlantic Citrus Property Owners Association and other agencies. Reference contractors are not affiliated with Epic Estates Palm Bay 12, LLC. Before you buy or build, confirm every requirement with the agency involved and talk to a Florida real estate attorney. Buyers must do their own due diligence.

Permitting

Building a homestead here means getting sign-off from several groups: the property owners' association, the county, the water management district, the state and the power company. None of it is unusual for rural Florida, and other owners in this area are going through the same process right now. The key is doing things in the right order, because a few approvals have to come before others.

This section walks through every permit and approval we know of for a typical homesite: house, barn, well, septic, power, driveway and pond. Where something hasn't been confirmed, we say so and tell you who to ask.

Where the property is

  • Jurisdiction: unincorporated Indian River County. The tracts are not inside the City of Fellsmere; the city limits lie just west of the Fellsmere Water Control District canal. County offices handle zoning and building permits.
  • Subdivision: Fellsmere Farms Company Subdivision, Plat Book 2, Pages 1–2 (originally recorded in St. Lucie County).
  • Zoning: A-2 (Agricultural), which allows up to one home per 10 acres.
  • Property owners' association: every tract is in the Florida Atlantic Citrus Property Owners Association (FACPOA). Membership is mandatory and the association's rules affect what you can build.
  • Roads: the east–west streets (115th–122nd) are private 40-ft rights-of-way. Access past the 121st Street area is through a private gate.

Before you buy: five things to confirm

These can stop a project outright, so check them before closing.

  • Can you build a house on this tract? A-2 allows one home per 10 acres, and many tracts here are a little under 10 acres. Older platted lots like these are often treated as "nonconforming lots of record" that can still be built on, but we have not confirmed this. Ask Indian River County Planning & Development about your specific parcel and get the answer in writing.
  • Is your access legal and insurable? The POA declaration grants members access over the private roads "for all purposes associated with operation and maintenance of a citrus grove." Have your attorney or title insurer confirm that this covers residential access. See our recommended contacts.
  • Where are the wetlands? A wetland delineation shows how much of your tract is usable. See Wetlands. See our recommended contacts.
  • Can you get power, and what will it cost? Some tracts are far from existing lines. Get an FPL estimate early. See Electric service.
  • Is the POA in good standing with you? Get an estoppel letter from FACPOA at closing showing any assessments owed, and ask about well consent and the house approval process (below).

Who approves what

WhoWhat they approve
FACPOA (the POA)House plans and site improvements, the water-management permit modification, well consent, driveway culverts into common areas
Indian River CountyZoning and buildability, address, building/electrical/plumbing/gas permits, floodplain review, inspections and certificate of occupancy, site work permits
St. Johns River Water Management District (SJRWMD)Stormwater permit modification for each house (filed through the POA); wetlands
Florida Department of Health in Indian River CountyWells under 6" diameter
Florida DEP and/or Department of HealthSeptic systems (the program is moving from Health to DEP)
Fellsmere Water Control DistrictWork in or near its canals and ditches, including crossings
FPLNew electric service and line extensions

The order to do things in

The steps run in one sequence: the first three happen before you buy, and the rest after closing.

  1. Before buying
  2. Do your due diligence: confirm buildability, access, flood zone, wetlands, power availability and POA standing (see the checklist above).
  3. Talk to a contractor about what you want to build, a rough budget and timeline, and anything about the tract that could add cost (fill, road raising, power). See our recommended contacts.
  4. Survey, wetland line and a soil boring at the planned house pad. See our recommended contacts.
  5. After closing, before construction
  6. Get an address assigned for the site.
  7. Hire a civil engineer for the site plan: house pad, pond and stormwater, outfall, swales, driveway, grading, flood elevation and road-raising design. See our recommended contacts.
  8. Submit to the POA. FACPOA reviews your plans, you pay its modification fee, and it files the SJRWMD permit modification.
  9. In parallel: well permit (plus POA consent), septic permit, FPL service request, clearing/excavation permits, and driveway/culvert approvals.
  10. Site work: clear, dig the pond, place fill for pads, and raise the access road.
  11. Building permit for the house, plus electrical, plumbing, mechanical and gas permits, with elevation certificates at the required stages.
  12. Inspections, then the certificate of occupancy.
  13. A barn can often go up earlier under the farm-building exemption (see Barns).

Permit by permit

1. POA approval and the water-management permit

This is your first stop for a house. The POA's recorded declaration (current version: Amended & Restated Declaration, Official Records Book 2459, Page 1625, recorded 2010) says a house can't be built until the POA gets a modification of the St. Johns River Water Management District's master stormwater permit No. 4-061-18774 to allow it.

  • Submit plans and specifications for the house and site improvements (stormwater pond, outfall, swales, driveway, grading) to the POA board.
  • Pay the POA's permit-modification fee. The board sets the amount; ask for the current fee.
  • Expect to need a civil engineer. Recent modifications included signed stormwater calculations, an operation and maintenance plan with costs, site plans, fee receipts and sometimes the owner's recorded deed. See our recommended contacts.

How long it takes: about 25 modifications have been approved since 2010, most for single lots. Recent ones (2025–2026) took between about 3 weeks and 4 months from application to staff report.

The district modifies this permit regularly as owners here build homes. To see the recent modifications yourself:

  1. Go to the SJRWMD e-permitting portal.
  2. Click Search > Regulatory Search.
  3. Enter 18774 in the Application/Permit # box.
  4. Click Search.

At the time of writing, the most recent modifications are from June 2026.

2. Raising the access road

Under the declaration, no house can be built until the road to it is raised above the 25-year / 24-hour storm peak stage, at the owner's cost. The required elevation is likely defined in the SJRWMD permit documents. Have your engineer determine how much road your tract needs to raise and what it will cost. See our recommended contacts.

The declaration also says nothing may obstruct the flow of water or access over existing roads.

3. Zoning, address and temporary living

Contact Indian River County Planning & Development to:

  • Confirm your tract can be built on (see "Before you buy").
  • Confirm the uses you plan are allowed under A-2, such as a home, barns, or commercial horse boarding.
  • Ask about setbacks for the house, barn and accessory structures, including ground-mounted solar. We haven't listed numbers here; get current figures from the county.
  • Get an address assigned. Most permits, and FPL's service portal, need one. Ask the county how to apply.
  • If you want to live in an RV during construction, ask whether a temporary use permit is required.

4. Flood zone and elevation

  • The area is mapped as FEMA Zone A (FIRM panel 12061C0075H, effective 12/4/2012). Zone A means there is no published base flood elevation (BFE). Check your exact tract on the FEMA Flood Map Service Center.
  • In Zone A, the county's floodplain administrator can require data to establish a base flood elevation for your site, usually prepared by an engineer or surveyor. You will also need elevation certificates. See our recommended contacts.
  • Ask the county floodplain administrator how the BFE must be determined and whether the county requires freeboard (extra height above the BFE). We haven't confirmed the county's freeboard rule.
  • Owners commonly use fill dug from the stormwater pond to raise house pads. Strip topsoil and muck first, and get a soil boring at the pad.

5. Wetlands

  • The larger wetlands are separate POA-owned tracts ("less and except" areas on the survey). Smaller wetland features may extend onto private tracts.
  • The POA declaration prohibits impacting wetlands and bans mowing, grading or clearing within 25 ft of any wetland (except routine road and ditch maintenance). The 25 ft is measured from the actual wetland edge.
  • Get a wetland delineation before you lay out your site. See our recommended contacts.
  • Any wetland impact would need SJRWMD (and possibly U.S. Army Corps of Engineers) approval and would violate the declaration. Plan to avoid wetlands entirely.

6. Well

  • POA consent first: the declaration says no well may be drilled without the POA board's express written consent.
  • Well construction permit: for wells under 6" in diameter (a typical 4" home well), permits are handled by the Florida Department of Health in Indian River County under an agreement with SJRWMD. SJRWMD handles wells 6" and larger. Your licensed well driller normally pulls the permit. See our recommended contacts.
  • Keep the well a safe distance from the septic system (see below).

7. Septic

  • Who issues the permit: Florida is moving septic (OSTDS) permitting from the Department of Health to the Department of Environmental Protection, county by county, through December 2026. Check which agency is taking applications for Indian River County when you apply.
  • Nitrogen-reducing systems: since January 1, 2024, new septic systems in the Indian River Lagoon protection area must be nitrogen-reducing (ENR) systems, which cost more. Ask the permitting agency whether your tract falls inside that area.
  • Low ground and a high water table often mean a mound system or an aerobic treatment unit on raised fill. A septic contractor can design the system and handle the permit. See our recommended contacts.
  • Ask for the required setbacks between the septic system, your well and any pond or ditch.

8. Electric service

  • Many western and northern tracts have no nearby power. The nearest usable poles may be about a mile away and across a canal.
  • Start a request on the FPL Project Portal. A service planner will give you an estimate. The portal may not recognize a new address yet; if so, use a nearby address and include your parcel ID.
  • Line-extension cost: under Florida rule 25-6.064 and FPL's tariff (Section 6), you pay the estimated job cost minus four times the expected annual non-fuel revenue from your service. A standard overhead transformer, service drop and meter are included. If other customers connect to your extension within about three years, you may get a partial refund.
  • Canal crossings need drainage district approval (FPL usually handles this). Lines along POA roads or across other tracts need easements from the POA and those landowners.
  • You'll need a county electrical permit for your service and panel. Solar needs its own permit, and ground-mounted arrays count as accessory structures subject to setbacks. Off-grid solar is an alternative to a line extension.

9. Site work: clearing, pond, fill and driveway

  • The pond, outfall, swales and grading are part of the SJRWMD permit-modification package (step 1).
  • Ask the county whether your clearing, tree removal, pond excavation or fill placement needs a separate county permit, and at what size thresholds.
  • Driveway culverts: the POA decides the size and location of culverts and pipes under common areas, so get POA sign-off. Work in or near a Fellsmere Water Control District ditch likely also needs the district's approval; ask them.

10. Building permits and inspections

  • Apply to the Indian River County Building Division for the house permit, plus electrical, plumbing, mechanical and gas permits as needed.
  • Provide elevation certificates at the stages the county requires.
  • Pass inspections and get your certificate of occupancy.
  • Sheds, workshops, carports and shipping containers generally need county permits and must meet setbacks. Ask the county about any rules specific to containers.

11. Barns and farm buildings

  • Under Florida Statute 604.50, a nonresidential farm building on land used for bona fide agricultural purposes is exempt from the Florida Building Code and from county codes and fees.
  • Floodplain rules still apply. The exemption does not cover floodplain management requirements.
  • Ask the county what documentation it wants to recognize the exemption, and whether an agricultural classification from the Property Appraiser will help support it.
  • Any building people live in, even part-time, is not a farm building.

12. Fuel tanks and propane

  • Propane: a buried propane tank must be installed by a licensed LP gas contractor. See our recommended contacts. Ask the county whether it also needs a county permit.
  • Diesel or other fuel: Florida's aboveground storage tank rules (Chapter 62-762) apply to tanks over 550 gallons, so a smaller tank is generally outside them. County and fire code requirements may still apply.

Easements and setbacks to plan around

The seller's survey and the POA declaration show several strips where you can't build. Your surveyor will mark the ones that affect your tract. See our recommended contacts.

  • 20-ft ditch easements on each side of existing Fellsmere Water Control District ditches. These run along streets and block edges, not between tracts inside a block. No structures in these strips.
  • Canal rights-of-way: the 184-ft drainage right-of-way along the far west, and the Park Lateral canal right-of-way (east 175 ft of Tracts 328, 362, 428 and 465).
  • 60-ft drainage and access easements across the south 30 ft of Tracts 323–331, the north 30 ft of Tracts 359–367, parts of Tracts 426–430 and 463–467, and a described easement across Tracts 431 and 462.
  • Strips conveyed to the POA for drainage, irrigation and road right-of-way: the east 100 ft of Tracts 123, 223, 263, 322, 368, 422 and 471, and the north 60 ft of Tract 323.
  • POA wetland tracts carved out of several tracts, plus the 25-ft no-clearing buffer around every wetland.
  • County setbacks for the A-2 district; confirm with the county.

POA dues and obligations

  • Annual assessments are charged per acre, and the board can raise them. Special assessments need a two-thirds vote. Unpaid assessments accrue interest and become a lien.
  • The declaration runs to January 1, 2041, then renews automatically in 5-year periods unless two-thirds of voting power records a termination.
  • The restrictions can be enforced by the POA or by any owner. Read the full declaration (PDF) before you buy; it's public record.

Disclaimer: Lot lines shown are approximate. Reference contractors are not affiliated with Epic Estates Palm Bay 12, LLC. Utility costs, POA information and permitting information are provided for general reference only and are not guaranteed. Buyers must conduct their own due diligence before purchasing.